The path to OptaPlanner enlightenment starts in the logs
Do you want to understand what OptaPlanner is doing while it is solving? Which decisions it makes? When? And why? Do you want to open the box and take a look inside? If so, keep reading.
The Age of Enlightenment centered on the use of reason and the evidence of the senses. Similarly, OptaPlanner enlightenment starts with the use of reason and the evidence in the logs.
OK. That’s enough philosophy for this article… It’s time to open the box. Take a look at the log for the school timetabling AI quickstart:
12:18:04 INFO Solving started: time spent (196), best score (-38init/0hard/0soft), environment mode (REPRODUCIBLE), move thread count (NONE), random (JDK with seed 0). 12:18:04 INFO Construction Heuristic phase (0) ended: time spent (330), best score (0hard/-11soft), score calculation speed (4358/sec), step total (19). 12:18:34 INFO Local Search phase (1) ended: time spent (30000), best score (0hard/10soft), score calculation speed (12786/sec), step total (26654). 12:18:34 INFO Solving ended: time spent (30000), best score (0hard/10soft), score calculation speed (12663/sec), phase total (2), environment mode (REPRODUCIBLE), move thread count (NONE).
This is a lot of information, even on the INFO
level.
Let’s investigate each nugget of information in there, one by one:
When did the solver run?
The log shows when the solver started and when it ended:
12:18:04 INFO Solving started ... ... 12:18:34 INFO Solving ended ...
That’s useful in complex applications with other log lines intertwined.
What is the solver doing?
It also displays what the solver did while solving:
12:18:04 INFO Solving started ... 12:18:04 INFO Construction Heuristic phase (0) ended ... 12:18:34 INFO Local Search phase (1) ended ... 12:18:34 INFO Solving ended ...
It ran two algorithm phases sequentially:
-
Phase 0: a Construction Heuristic to provide an initial solution for the problem
-
Phase 1: a Local Search to improve the solution further
Here’s an illustration of those phases on the N-Queens and the Cloud Balancing examples:
If the Local Search log line is missing (after the solver ends), the Construction Heuristic did not have enough time to initialize the entire solution, leaving no time for the Local Search algorithm. That returns an incomplete or infeasible solution.
Time spent
The log also exhibits how long each of those phases took, in milliseconds, relevant to the start of the solver:
12:18:04 INFO Solving started time spent (196) ... 12:18:04 INFO Construction Heuristic ended ... time spent (330) ... 12:18:34 INFO Local Search ended ... time spent (30000) ... 12:18:34 INFO Solving ended time spent (30000), ...
-
The Solver initialization took
196
milliseconds. -
The Construction Heuristic took
330 - 196
=134
milliseconds.-
For big datasets, if the CH takes more than one minute, it’s worth investigating why, even if the solver runs for hours.
-
-
The Local Search took
30000 - 330
=29670
milliseconds.-
LS gets the lion’s share of the time, as it should be.
-
Score quality
The log also reveals the solution quality after each algorithm:
INFO Solving started ... best score (-38init/0hard/0soft) ... INFO Construction Heuristic ended ... best score (0hard/-11soft) ... INFO Local Search ended ... best score (0hard/10soft) ... INFO Solving ended ... best score (0hard/10soft) ...
-
The starting score
-38init/0hard/0soft
indicates there are 38 unassigned planning variables. That’s because there are 19 lessons, each with 2 planning variables to initialize. -
The Construction Heuristic ends with a solution of score
0hard/-11soft
, which is already feasible (no hard constraints broken). That’s not always the case. -
The Local Search improves the score further to score
0hard/10soft
. That’s a difference of+21soft
in 29 seconds.
Performance
There’s also performance information to discover in the log. First ensure it’s an apples-to-apples comparison:
12:18:04 INFO Solving started ... environment mode (REPRODUCIBLE), move thread count (NONE) ... ... 12:18:34 INFO Solving ended ... environment mode (REPRODUCIBLE), move thread count (NONE).
-
If the environment mode is any
ASSERT
mode, performance is irrelevant, because the extra assertions are very expensive performance wise. -
The move thread count indicates how many extra CPU cores it can consume.
-
NONE
means all move calculations happen inside the solver’s thread, so only 1 CPU is exploited.
-
Both of these affect the score calculation speed, which shows how many moves were evaluated, normalized per second, for the solver entirely, but also each phase separately:
12:18:04 INFO Solving started ... 12:18:04 INFO Construction Heuristic ended ... score calculation speed (4358/sec) ... 12:18:34 INFO Local Search ... score calculation speed (12786/sec) ... 12:18:34 INFO Solving ended ... score calculation speed (12663/sec) ...
-
The Construction Heuristic evaluated over 4000 moves per second.
-
That’s actually pretty low, but it only ran for 134 milliseconds, so the overhead weighs in too much, lowering the number significantly. It should be run with a bigger dataset instead.
-
Normally, the score calculation speed of the Construction Heuristic is higher than that of the Local Search, because it’s faster to calculate the score when half of the entities aren’t initialized yet.
-
-
The Local Search evaluated over 12000 moves per second.
-
That’s good. The LS score calculation speed should always be above 10 000 per second, even for big datasets.
-
Do note that it ran for 29 seconds and a JVM can take a minute to warm up.
-
Keep an eye on the score calculation when adding/editing constraints,
running the solver for same amount of time (typically 1 minute), to discover performance bottlenecks early.
For more accurate performance investigations, use optaplanner-benchmark
which supports warming up.
Steps
In essence, both the Construction Heuristic phase and Local Search phase run a double loop:
for (Step step : steps) { // Outer loop
for (Move move : moves) { // Inner loop
// Evaluate move
}
// Take step
}
The outer, step loop executes the best move found by the inner, move loop. Of course, this is a gross simplification: there are dozens of orthogonal AI subsystems on top of it. It’s only the tip of the iceberg. But it’s an honest simplification.
The INFO
log shows how many of these outer loop iterations both phases did:
... 12:18:04 INFO Construction Heuristic ended ... step total (19). 12:18:34 INFO Local Search ended ... step total (26654). ...
-
The Construction Heuristic did 19 steps. That’s because there are 19 lessons in the dataset. Each step assigns one lesson.
-
The Local Search did over 26 000 steps. It continues iterating until the termination condition is hit. Each step modifies (often improves) the current solution.
Turn on DEBUG
logging to get a log line per step too:
INFO Solving started: time spent (619), best score (-38init/0hard/0soft), environment mode (REPRODUCIBLE), move thread count (NONE), random (JDK with seed 0). DEBUG CH step (0), time spent (650), score (-36init/0hard/0soft), selected move count (30), picked move ([Biology(18) {null -> Room A}, Biology(18) {null -> MONDAY 09:30}]). DEBUG CH step (1), time spent (661), score (-34init/0hard/0soft), selected move count (30), picked move ([Chemistry(28) {null -> Room A}, Chemistry(28) {null -> MONDAY 10:30}]). DEBUG CH step (2), time spent (672), score (-32init/0hard/0soft), selected move count (30), picked move ([Chemistry(17) {null -> Room A}, Chemistry(17) {null -> MONDAY 13:30}]). ... DEBUG CH step (17), time spent (741), score (-2init/0hard/-10soft), selected move count (30), picked move ([Spanish(22) {null -> Room B}, Spanish(22) {null -> TUESDAY 10:30}]). DEBUG CH step (18), time spent (744), score (0hard/-11soft), selected move count (30), picked move ([Spanish(23) {null -> Room B}, Spanish(23) {null -> TUESDAY 14:30}]). INFO Construction Heuristic phase (0) ended: time spent (768), best score (0hard/-11soft), score calculation speed (3910/sec), step total (19). DEBUG LS step (0), time spent (790), score (0hard/-5soft), new best score (0hard/-5soft), accepted/selected move count (1/1), picked move (Physics(27) {Room B, MONDAY 08:30} <-> Math(14) {Room A, MONDAY 08:30}). DEBUG LS step (1), time spent (791), score (0hard/-7soft), best score (0hard/-5soft), accepted/selected move count (1/2), picked move (Spanish(33) {Room B -> Room C}). ... DEBUG LS step (19071), time spent (29996), score (0hard/7soft), best score (0hard/10soft), accepted/selected move count (1/25), picked move (Geography(30) {Room C -> Room B}). DEBUG LS step (19072), time spent (30000), score (0hard/5soft), best score (0hard/10soft), accepted/selected move count (0/25), picked move (English(20) {Room A, MONDAY 10:30} <-> Math(14) {Room A, MONDAY 14:30}). INFO Local Search phase (1) ended: time spent (30000), best score (0hard/10soft), score calculation speed (7927/sec), step total (19073). INFO Solving ended: time spent (30000), best score (0hard/10soft), score calculation speed (7858/sec), phase total (2), environment mode (REPRODUCIBLE), move thread count (NONE).
Again, this is a lot of information to digest.
The DEBUG
lines display when a Local Search step improves the best solution:
INFO Construction Heuristic ... best score (0hard/-11soft) ... DEBUG LS step (0) ... score (0hard/-5soft), new best score (0hard/-5soft) ... DEBUG LS step (1) ... score (0hard/-7soft), best score (0hard/-5soft) ... ...
-
LS step 0 improved the best solution from
-11soft
to-5soft
. -
LS step 1 didn’t improve the best solution of
-5soft
.-
It actually accepted a worse solution of
-7soft
, which is mechanism to escape local optima, to improve the best solutions in later steps.
-
The DEBUG
log even shows the winning move:
DEBUG LS step (0) ... picked move (Physics(27) {Room B, MONDAY 08:30} <-> Math(14) {Room A, MONDAY 08:30}).
This move swapped the Physics
lesson with the Math
lesson.
The toString()
method of your domain classes should return a short string (typically a name and/or ID)
to keep the logs readable.
Moves
The DEBUG
log reveals the number of moves selected per step,
which is the number of inner loop iterations:
... DEBUG CH step (17) ... selected move count (30) ... DEBUG CH step (18) ... selected move count (30) ... INFO Construction Heuristic ended ... DEBUG LS step (0) ... accepted/selected move count (1/1) ... DEBUG LS step (1) ... accepted/selected move count (1/2) ... ... INFO Local Search phase (1) ended ...
Turn on TRACE
logging to get a log line per move too,
which exposes the score of each move evaluation:
INFO Construction Heuristic ... time spent (395), best score (0hard/-11soft) ... TRACE Move index (0), score (0hard/-5soft) ... DEBUG LS step (0) ... score (0hard/-5soft), new best score (0hard/-5soft) ... TRACE Move index (0), score (-2hard/-6soft) ... TRACE Move index (1), score (0hard/-7soft) ... DEBUG LS step (1) ... score (0hard/-7soft), best score (0hard/-5soft) ... TRACE Move index (0), score (-3hard/-7soft) ... TRACE Move index (1) not doable, ignoring move ... TRACE Move index (2), score (-2hard/-9soft) ... TRACE Move index (3), score (-2hard/-6soft) ... TRACE Move index (4), score (-2hard/-7soft) ... TRACE Move index (5), score (-1hard/-8soft) ... TRACE Move index (6), score (0hard/-4soft) ... DEBUG LS step (2) ... score (0hard/-4soft), new best score (0hard/-4soft) ...
Again, each TRACE
line also shows the selected move:
TRACE Move index (0) ... move (Chemistry(28) {Room C -> Room A}).
This move changed the room of the Chemistry
lesson.
Get started
Get started on your OptaPlanner enlightenment path today!
Turn on logging in:
-
Plain Java: Add a dependency on
logback-classic
and thelogback.xml
file:<configuration> <logger name="org.optaplanner" level="debug"/> </configuration>
Or instead, add a dependency on an
slf4j
bridge to your favorite logging system. -
Quarkus: Add this line in
application.properties
:quarkus.log.category."org.optaplanner".level=DEBUG
-
Spring Boot: Add this line in
application.properties
:logging.level.org.optaplanner=DEBUG
The log is your friend! It tells you what OptaPlanner is doing. Keep an eye on it.